Calendar An icon of a desk calendar. Cancel An icon of a circle with a diagonal line across. Caret An icon of a block arrow pointing to the right. Email An icon of a paper envelope. Facebook An icon of the Facebook "f" mark. Google An icon of the Google "G" mark. Linked In An icon of the Linked In "in" mark. Logout An icon representing logout. Profile An icon that resembles human head and shoulders. Telephone An icon of a traditional telephone receiver. Tick An icon of a tick mark. Is Public An icon of a human eye and eyelashes. Is Not Public An icon of a human eye and eyelashes with a diagonal line through it. Pause Icon A two-lined pause icon for stopping interactions. Quote Mark A opening quote mark. Quote Mark A closing quote mark. Arrow An icon of an arrow. Folder An icon of a paper folder. Breaking An icon of an exclamation mark on a circular background. Camera An icon of a digital camera. Caret An icon of a caret arrow. Clock An icon of a clock face. Close An icon of the an X shape. Close Icon An icon used to represent where to interact to collapse or dismiss a component Comment An icon of a speech bubble. Comments An icon of a speech bubble, denoting user comments. Comments An icon of a speech bubble, denoting user comments. Ellipsis An icon of 3 horizontal dots. Envelope An icon of a paper envelope. Facebook An icon of a facebook f logo. Camera An icon of a digital camera. Home An icon of a house. Instagram An icon of the Instagram logo. LinkedIn An icon of the LinkedIn logo. Magnifying Glass An icon of a magnifying glass. Search Icon A magnifying glass icon that is used to represent the function of searching. Menu An icon of 3 horizontal lines. Hamburger Menu Icon An icon used to represent a collapsed menu. Next An icon of an arrow pointing to the right. Notice An explanation mark centred inside a circle. Previous An icon of an arrow pointing to the left. Rating An icon of a star. Tag An icon of a tag. Twitter An icon of the Twitter logo. Video Camera An icon of a video camera shape. Speech Bubble Icon A icon displaying a speech bubble WhatsApp An icon of the WhatsApp logo. Information An icon of an information logo. Plus A mathematical 'plus' symbol. Duration An icon indicating Time. Success Tick An icon of a green tick. Success Tick Timeout An icon of a greyed out success tick. Loading Spinner An icon of a loading spinner. Facebook Messenger An icon of the facebook messenger app logo. Facebook An icon of a facebook f logo. Facebook Messenger An icon of the Twitter app logo. LinkedIn An icon of the LinkedIn logo. WhatsApp Messenger An icon of the Whatsapp messenger app logo. Email An icon of an mail envelope. Copy link A decentered black square over a white square.

Green light for Madras College still awaited as work on access road begins

An artist's impression of how the new Madras College will look.
An artist's impression of how the new Madras College will look.

Concern has been voiced that a flagship and long-awaited new school is yet to be given planning permission, as work begins on construction of the access road.

Fife Council intends to have a new £50 million Madras College school ready by early summer 2021.

It is estimated erection of the 1,450-pupil school will take two years but the project is yet to be given the green light by a planning committee.

And a deadline for determining the St Andrews West expansion master plan – which must be approved before the school – has been extended until December.

Construction workers arrived at the North Haugh last Monday to start building part of the St Andrews West link road, which will allow access to the school site at Langlands.

St Andrews councillor Brian Thomson said: “While it’s great to see progress on the ground, the fact that planning permission has not yet been granted for the school is obviously a bit of a concern.

“It’s also concerning that the St Andrews West consortium has recently requested a three-month extension for consideration of the master plan until December.”

The site of the school forms part of the St Andrews West strategic development zone, where more than 1,000 houses are planned, as well as university expansion, a business park, employment land and community facilities.

Planning permission for the school to be built at Pipeland, next to the town’s hospital, was quashed following a legal challenge.

Mr Thomson said finalising the master plan was clearly a complex matter, with transportation links, landscaping, drainage and other infrastructure to be assessed, negotiated and determined.

He said: “I can appreciate the council officers’ desire to mitigate the risk of any legal challenge, particularly given the track record of such action being taken in relation to planning decisions in St Andrews, and their caution in the handling of the planning applications is understandable.

“However, it’s encouraging that officers are still of the view that the delivery of a new school is achievable within the 2020/21 academic year, which — given that it will take around two years to construct the school — would seem to suggest that the determination of the planning applications can’t be too far away.

“Constructing a new school within that timescale would be excellent but, if it’s not, I would certainly hope that a new school could be delivered by August 2021.”

Pam Ewen, the council’s senior manager in planning, said: “Both planning applications for the new secondary school and the larger development area across St Andrews West are still being considered by the planning authority.

“The St Andrews West application has an extension of three months until early December which was agreed at the request of the applicant.

“A date for the consideration of either of these applications has not been set and we continue to assess the applications.”

Alan Paul, property services senior manager, said: “The council remains committed to delivering the new Madras as soon as possible and that we continue to target delivery during the academic year 2020/21.”