Calendar An icon of a desk calendar. Cancel An icon of a circle with a diagonal line across. Caret An icon of a block arrow pointing to the right. Email An icon of a paper envelope. Facebook An icon of the Facebook "f" mark. Google An icon of the Google "G" mark. Linked In An icon of the Linked In "in" mark. Logout An icon representing logout. Profile An icon that resembles human head and shoulders. Telephone An icon of a traditional telephone receiver. Tick An icon of a tick mark. Is Public An icon of a human eye and eyelashes. Is Not Public An icon of a human eye and eyelashes with a diagonal line through it. Pause Icon A two-lined pause icon for stopping interactions. Quote Mark A opening quote mark. Quote Mark A closing quote mark. Arrow An icon of an arrow. Folder An icon of a paper folder. Breaking An icon of an exclamation mark on a circular background. Camera An icon of a digital camera. Caret An icon of a caret arrow. Clock An icon of a clock face. Close An icon of the an X shape. Close Icon An icon used to represent where to interact to collapse or dismiss a component Comment An icon of a speech bubble. Comments An icon of a speech bubble, denoting user comments. Comments An icon of a speech bubble, denoting user comments. Ellipsis An icon of 3 horizontal dots. Envelope An icon of a paper envelope. Facebook An icon of a facebook f logo. Camera An icon of a digital camera. Home An icon of a house. Instagram An icon of the Instagram logo. LinkedIn An icon of the LinkedIn logo. Magnifying Glass An icon of a magnifying glass. Search Icon A magnifying glass icon that is used to represent the function of searching. Menu An icon of 3 horizontal lines. Hamburger Menu Icon An icon used to represent a collapsed menu. Next An icon of an arrow pointing to the right. Notice An explanation mark centred inside a circle. Previous An icon of an arrow pointing to the left. Rating An icon of a star. Tag An icon of a tag. Twitter An icon of the Twitter logo. Video Camera An icon of a video camera shape. Speech Bubble Icon A icon displaying a speech bubble WhatsApp An icon of the WhatsApp logo. Information An icon of an information logo. Plus A mathematical 'plus' symbol. Duration An icon indicating Time. Success Tick An icon of a green tick. Success Tick Timeout An icon of a greyed out success tick. Loading Spinner An icon of a loading spinner. Facebook Messenger An icon of the facebook messenger app logo. Facebook An icon of a facebook f logo. Facebook Messenger An icon of the Twitter app logo. LinkedIn An icon of the LinkedIn logo. WhatsApp Messenger An icon of the Whatsapp messenger app logo. Email An icon of an mail envelope. Copy link A decentered black square over a white square.

Transport chief tight-lipped on A9 and A96 dualling projects

A9 dualling works between Luncarty and Birnam.

Transport bosses expect to confirm this year if the current timescales for dualling the A9 and A96 “remain deliverable”.

MSPs on the Scottish Parliament’s public audit committee grilled Bill Reeve, director of rail at Transport Scotland, on the progress of both infrastructure projects.

Former Cabinet Secretary for Infrastructure Alex Neil said he is “absolutely perplexed” that he could not get an answer on the estimated completion date for both projects.

Alex Neil.

When asked if the policy is still to complete the A9 Perth to Inverness road by 2025 and the A96 Aberdeen to Inverness route by 2030 or if they were being “quietly shoved into the long grass”, Mr Reeve said “absolutely not”.

He added: “We remain absolutely committed to the delivery of the A9 and A96 as soon as is practicably possible.”

The director of rail added that a revised assessment will be carried out, taking in the impact of Covid-19 and engagement with the construction industry, but said it is “unlikely to be before the summer” that it is made available.

Mr Reeve said: “It is my expectation that later this year it will be possible to confirm whether the current targets remain deliverable or whether there is to be any alteration to those.

“At the minute we are continuing to work to recover programmes, where possible, where they have slipped and to press on with the development work I have outlined.”

It follows an admission from the first minister this month that proposals to dual both roads were “ambitious”, with Covid-19 having impacted on projected timescales.

Work is ‘pressing on’

The two schemes, which are expected to cost at least £6 billion, have faced lockdown setbacks, with only one section of the A9 complete so far and construction yet to start on the A96.

The first section of the A9 works between Kincraig and Dalraddy is complete, with work having restarted on the second section between Luncarty and the Pass of Birnham, following a temporary halt due to coronavirus restrictions.

Mr Reeve said “work is pressing on” with the remaining sections of the road with officials still engaged in the statutory procedures to determine its alignment.

A9 dualling timescale
Members of the public study the proposed route at a public exhibition held in Elgin, Moray.

On the A96, the transport boss said the statutory consents process is “under way”.

He added there was “good progress” on the Fochabers to east of Huntly section and that the east of Huntly to Aberdeen virtual exhibition has been extended until March 8 due to a high level of interest from the public – with it drawing  18,000 visits online.