Calendar An icon of a desk calendar. Cancel An icon of a circle with a diagonal line across. Caret An icon of a block arrow pointing to the right. Email An icon of a paper envelope. Facebook An icon of the Facebook "f" mark. Google An icon of the Google "G" mark. Linked In An icon of the Linked In "in" mark. Logout An icon representing logout. Profile An icon that resembles human head and shoulders. Telephone An icon of a traditional telephone receiver. Tick An icon of a tick mark. Is Public An icon of a human eye and eyelashes. Is Not Public An icon of a human eye and eyelashes with a diagonal line through it. Pause Icon A two-lined pause icon for stopping interactions. Quote Mark A opening quote mark. Quote Mark A closing quote mark. Arrow An icon of an arrow. Folder An icon of a paper folder. Breaking An icon of an exclamation mark on a circular background. Camera An icon of a digital camera. Caret An icon of a caret arrow. Clock An icon of a clock face. Close An icon of the an X shape. Close Icon An icon used to represent where to interact to collapse or dismiss a component Comment An icon of a speech bubble. Comments An icon of a speech bubble, denoting user comments. Comments An icon of a speech bubble, denoting user comments. Ellipsis An icon of 3 horizontal dots. Envelope An icon of a paper envelope. Facebook An icon of a facebook f logo. Camera An icon of a digital camera. Home An icon of a house. Instagram An icon of the Instagram logo. LinkedIn An icon of the LinkedIn logo. Magnifying Glass An icon of a magnifying glass. Search Icon A magnifying glass icon that is used to represent the function of searching. Menu An icon of 3 horizontal lines. Hamburger Menu Icon An icon used to represent a collapsed menu. Next An icon of an arrow pointing to the right. Notice An explanation mark centred inside a circle. Previous An icon of an arrow pointing to the left. Rating An icon of a star. Tag An icon of a tag. Twitter An icon of the Twitter logo. Video Camera An icon of a video camera shape. Speech Bubble Icon A icon displaying a speech bubble WhatsApp An icon of the WhatsApp logo. Information An icon of an information logo. Plus A mathematical 'plus' symbol. Duration An icon indicating Time. Success Tick An icon of a green tick. Success Tick Timeout An icon of a greyed out success tick. Loading Spinner An icon of a loading spinner. Facebook Messenger An icon of the facebook messenger app logo. Facebook An icon of a facebook f logo. Facebook Messenger An icon of the Twitter app logo. LinkedIn An icon of the LinkedIn logo. WhatsApp Messenger An icon of the Whatsapp messenger app logo. Email An icon of an mail envelope. Copy link A decentered black square over a white square.

Angus schools project cost up £1.6 million before construction starts

Angus schools project cost up £1.6 million before construction starts

The cost of a controversial Angus schools project has rocketed by more than £1.6 million before a brick has been laid.

The rising cost of the Arbroath Schools Project will go before councillors at a meeting today, during which the aftershock of Muirfield Contracts’ demise will be felt.

The replacement programme was born from the wreckage of proposals for an £8m “superschool” merging Timmergreens and Muirfield primaries on the Westway.

New Timmergreens and Warddykes primaries were originally slated to cost £10.6m with the new revised estimates at £12.2m.

The figures come as the search begins for an alternative contractor to build the schools, with a local councillor’s “cast-iron assurance” still echoing from last week’s shock developments at Muirfield Contracts.

The Dundee-based firm was appointed by Hub East Central Scotland known as Hubco to build replacement primaries at Timmergreens and Warddykes.

Almost 260 workers and more than 100 self-employed contractors found themselves out of work last week after Muirfield collapsed and administrators confirmed nothing could be done to revive the business.

Angus Council previously announced the new schools would be delayed by about six weeks, which was “outwith” its control as the contractor is appointed by the Scottish Future Trust’s procurement agent.

The procurement phase is necessary as £600,000 of the cost will be paid by the trust.

A spokesman for Hub East Central Scotland said: “We are working with Angus Council to put in place a solution as soon as possible that will ensure the schools project goes ahead with the minimum of delay.

“It would be inappropriate to make any further comment until those plans are finalised.”

Members of the local authority’s policy and resources committee will meet at the Cross in Forfar today.

In his report, Transforming Angus service manager Gordon Cargill states the council is “still waiting on firm proposals” from Hubco.

He adds: “However, there is now a target to achieve financial close by the end of March 2015, leading to a start on site as soon as possible thereafter

“Members should note that a further report will be presented to the council with the updated cost position after Hubco have finalised the contract with the new main contractor.”

The cost implications of changing contractor were discussed during a private item at the last meeting of the full Angus Council last month.

As of today, the new-build Timmergreens would cost £4.9m and Warddykes £6.3m including £250,000 for demolition; while improvement for Muirfield, to which Timmergreens staff and pupils have decanted, will cost £390,000 along with £527,000 in “temporary accommodation” costs.

The “abortive design fees” from Hospitalfield cost £104,000 a total cost of £12,276,000.

Units at Muirfield PS may be sold off or used for future improvements at Ladyloan and Inverbrothock primaries.

Mr Cargill adds: “The above information highlights that the £12.276m gross costs to date also include elements that are attributable to long-term improvements to Muirfield.”