Calendar An icon of a desk calendar. Cancel An icon of a circle with a diagonal line across. Caret An icon of a block arrow pointing to the right. Email An icon of a paper envelope. Facebook An icon of the Facebook "f" mark. Google An icon of the Google "G" mark. Linked In An icon of the Linked In "in" mark. Logout An icon representing logout. Profile An icon that resembles human head and shoulders. Telephone An icon of a traditional telephone receiver. Tick An icon of a tick mark. Is Public An icon of a human eye and eyelashes. Is Not Public An icon of a human eye and eyelashes with a diagonal line through it. Pause Icon A two-lined pause icon for stopping interactions. Quote Mark A opening quote mark. Quote Mark A closing quote mark. Arrow An icon of an arrow. Folder An icon of a paper folder. Breaking An icon of an exclamation mark on a circular background. Camera An icon of a digital camera. Caret An icon of a caret arrow. Clock An icon of a clock face. Close An icon of the an X shape. Close Icon An icon used to represent where to interact to collapse or dismiss a component Comment An icon of a speech bubble. Comments An icon of a speech bubble, denoting user comments. Comments An icon of a speech bubble, denoting user comments. Ellipsis An icon of 3 horizontal dots. Envelope An icon of a paper envelope. Facebook An icon of a facebook f logo. Camera An icon of a digital camera. Home An icon of a house. Instagram An icon of the Instagram logo. LinkedIn An icon of the LinkedIn logo. Magnifying Glass An icon of a magnifying glass. Search Icon A magnifying glass icon that is used to represent the function of searching. Menu An icon of 3 horizontal lines. Hamburger Menu Icon An icon used to represent a collapsed menu. Next An icon of an arrow pointing to the right. Notice An explanation mark centred inside a circle. Previous An icon of an arrow pointing to the left. Rating An icon of a star. Tag An icon of a tag. Twitter An icon of the Twitter logo. Video Camera An icon of a video camera shape. Speech Bubble Icon A icon displaying a speech bubble WhatsApp An icon of the WhatsApp logo. Information An icon of an information logo. Plus A mathematical 'plus' symbol. Duration An icon indicating Time. Success Tick An icon of a green tick. Success Tick Timeout An icon of a greyed out success tick. Loading Spinner An icon of a loading spinner. Facebook Messenger An icon of the facebook messenger app logo. Facebook An icon of a facebook f logo. Facebook Messenger An icon of the Twitter app logo. LinkedIn An icon of the LinkedIn logo. WhatsApp Messenger An icon of the Whatsapp messenger app logo. Email An icon of an mail envelope. Copy link A decentered black square over a white square.

Weather conditions could delay full launch of world’s largest offshore wind farm

Dogger Bank produced its first electricity in October last year (Ben Birchall/PA)
Dogger Bank produced its first electricity in October last year (Ben Birchall/PA)

The full opening of the world’s largest offshore wind farm, off the north-east coast of England, could be delayed, the company behind it has said.

SSE said that bad weather and delays in its supply chains could push the full operations of the Dogger Bank A site into 2025.

The wind farm had originally started producing its first power in October last year, with commercial operations set to start this year.

“However, turbine installation on Dogger Bank A has been affected by challenging weather conditions with vessel availability and supply chain delays further impacting progress,” SSE said.

“Following notification of further vessel unavailability over the coming weeks there is an increasing possibility that full operations will not be achieved until 2025, although this is not expected to materially change project returns.”

The Dogger Bank site is going to be built in three phases, each with nearly 100 wind turbines and supplying 1.2 gigawatts (GW) of wind capacity.

By 2026 it is expected to be powering around six million homes per year.

The companies behind it, SSE and Equinor, are also exploring the potential for a fourth phase, which could increase its capacity even further.

SSE separately said that 10 storms over the three months to the end of December hit the amount of renewable electricity it produced.

Output from SSE Renewables in the nine months to the end of December was around 15% below what had been planned.

Production was also hit by outages at some of its plants, the business said.

“While the quarter has seen the business navigate some short-term challenges, we reiterate and continue to focus on the delivery of our 2027 financial and operational growth targets,” said finance boss Barry O’Regan.

“The strength of our balanced business mix and the growth opportunity it provides is aligned with a policy environment which increasingly recognises the essential role renewables, electricity networks and flexible power will play in the energy system of the future.

“Our long-term strategy remains unchanged and will deliver sustainable value for shareholders and society.”