Calendar An icon of a desk calendar. Cancel An icon of a circle with a diagonal line across. Caret An icon of a block arrow pointing to the right. Email An icon of a paper envelope. Facebook An icon of the Facebook "f" mark. Google An icon of the Google "G" mark. Linked In An icon of the Linked In "in" mark. Logout An icon representing logout. Profile An icon that resembles human head and shoulders. Telephone An icon of a traditional telephone receiver. Tick An icon of a tick mark. Is Public An icon of a human eye and eyelashes. Is Not Public An icon of a human eye and eyelashes with a diagonal line through it. Pause Icon A two-lined pause icon for stopping interactions. Quote Mark A opening quote mark. Quote Mark A closing quote mark. Arrow An icon of an arrow. Folder An icon of a paper folder. Breaking An icon of an exclamation mark on a circular background. Camera An icon of a digital camera. Caret An icon of a caret arrow. Clock An icon of a clock face. Close An icon of the an X shape. Close Icon An icon used to represent where to interact to collapse or dismiss a component Comment An icon of a speech bubble. Comments An icon of a speech bubble, denoting user comments. Comments An icon of a speech bubble, denoting user comments. Ellipsis An icon of 3 horizontal dots. Envelope An icon of a paper envelope. Facebook An icon of a facebook f logo. Camera An icon of a digital camera. Home An icon of a house. Instagram An icon of the Instagram logo. LinkedIn An icon of the LinkedIn logo. Magnifying Glass An icon of a magnifying glass. Search Icon A magnifying glass icon that is used to represent the function of searching. Menu An icon of 3 horizontal lines. Hamburger Menu Icon An icon used to represent a collapsed menu. Next An icon of an arrow pointing to the right. Notice An explanation mark centred inside a circle. Previous An icon of an arrow pointing to the left. Rating An icon of a star. Tag An icon of a tag. Twitter An icon of the Twitter logo. Video Camera An icon of a video camera shape. Speech Bubble Icon A icon displaying a speech bubble WhatsApp An icon of the WhatsApp logo. Information An icon of an information logo. Plus A mathematical 'plus' symbol. Duration An icon indicating Time. Success Tick An icon of a green tick. Success Tick Timeout An icon of a greyed out success tick. Loading Spinner An icon of a loading spinner. Facebook Messenger An icon of the facebook messenger app logo. Facebook An icon of a facebook f logo. Facebook Messenger An icon of the Twitter app logo. LinkedIn An icon of the LinkedIn logo. WhatsApp Messenger An icon of the Whatsapp messenger app logo. Email An icon of an mail envelope. Copy link A decentered black square over a white square.

Angus Council’s schools project has avoided worst of Muirfield Contracts’ collapse

An artist's impression of the replacement primary school at Timmergreens.
An artist's impression of the replacement primary school at Timmergreens.

The collapse of Tayside building firm Muirfield Contracts is “unfortunate” but does not represent a terminal blow for the controversial Arbroath schools project, councillors say.

Work on replacement schools at Timmergreens and Warddykes primaries has stalled due to the construction firm’s financial difficulties.

However, Angus councillors insisted the huge project remains on track, with agency Hubco now set to handle the appointment of a replacement construction firm.

Question marks remain, however, over the cost of appointing a new contractor.

Councillor Alex King expressed relief that Muirfield were not on site when their crippling financial difficulties resulted in the administrators being called in.

“We would have been in a far worse position if we had come to financial close and Muirfield had actually been on site,” he said.

“As it is we have only marginal exposure to unfinished contracts with Muirfield.”

Mr King said there “may or may not be further increases in cost” as the council has to go to the second contractor.

“Once we have financial close or a final price we will be bringing it back to committee,” he continued.

“One thing I will say here and now. This is a priority project and there is no question of these schools not being rebuilt.”

Members of the local authority’s policy and resources committee met at the Cross in Forfar.

They heard the council is “still waiting on firm proposals” from Hubco, with hopes that a contractor will be appointed by the end of this month.

Should the estimates for the project now at £12.2 million increase by more than 5% then councillors will be asked to approve the extra capital funding.

Fellow Arbroath councillor David Fairweather supported the report and stated “the past is in the past” with reference to the long and difficult battle over conflicting plans for Arbroath’s schools estate.

The replacement programme was born from the wreckage of proposals for an £8m “superschool” merging Timmergreens and Muirfield primaries on the Westway.

Arbroath councillor and children and learning convener Sheena Welsh said the council is “very lucky” to have encountered a delay rather than a false start with building works.

She added: “We could easily have a contract disappear four weeks into it.

“Muirfield is a contractor that we’ve used before, and it has built schools for us before.

“So, if we had been completely on our own there is a distinct possibility we would have appointed them as contractor.

“It’s very bad news for the Muirfield workers and I feel very sorry for them I feel relieved from the council’s point of view.”

Almost 260 workers and more than 100 self-employed contractors found themselves out of work last week after Muirfield collapsed and administrators confirmed nothing could be done to revive the business.

Angus Council previously announced the new schools would be delayed by about six weeks, which was “outwith” its control as the contractor is appointed by the Scottish Future Trust’s procurement agent.

The procurement phase is necessary as £600,000 of the cost will be paid by the trust.

The new-build Timmergreens would cost £4.9m and Warddykes £6.3m including £250,000 for demolition; while improvement for Muirfield, to which Timmergreens staff and pupils have decanted, will cost £390,000 along with £527,000 in “temporary accommodation” costs.

The “abortive design fees” from Hospitalfield cost £104,000 a total cost of £12,276,000.

Units at Muirfield PS may be sold off or used for future improvements at Ladyloan and Inverbrothock primaries.