Calendar An icon of a desk calendar. Cancel An icon of a circle with a diagonal line across. Caret An icon of a block arrow pointing to the right. Email An icon of a paper envelope. Facebook An icon of the Facebook "f" mark. Google An icon of the Google "G" mark. Linked In An icon of the Linked In "in" mark. Logout An icon representing logout. Profile An icon that resembles human head and shoulders. Telephone An icon of a traditional telephone receiver. Tick An icon of a tick mark. Is Public An icon of a human eye and eyelashes. Is Not Public An icon of a human eye and eyelashes with a diagonal line through it. Pause Icon A two-lined pause icon for stopping interactions. Quote Mark A opening quote mark. Quote Mark A closing quote mark. Arrow An icon of an arrow. Folder An icon of a paper folder. Breaking An icon of an exclamation mark on a circular background. Camera An icon of a digital camera. Caret An icon of a caret arrow. Clock An icon of a clock face. Close An icon of the an X shape. Close Icon An icon used to represent where to interact to collapse or dismiss a component Comment An icon of a speech bubble. Comments An icon of a speech bubble, denoting user comments. Comments An icon of a speech bubble, denoting user comments. Ellipsis An icon of 3 horizontal dots. Envelope An icon of a paper envelope. Facebook An icon of a facebook f logo. Camera An icon of a digital camera. Home An icon of a house. Instagram An icon of the Instagram logo. LinkedIn An icon of the LinkedIn logo. Magnifying Glass An icon of a magnifying glass. Search Icon A magnifying glass icon that is used to represent the function of searching. Menu An icon of 3 horizontal lines. Hamburger Menu Icon An icon used to represent a collapsed menu. Next An icon of an arrow pointing to the right. Notice An explanation mark centred inside a circle. Previous An icon of an arrow pointing to the left. Rating An icon of a star. Tag An icon of a tag. Twitter An icon of the Twitter logo. Video Camera An icon of a video camera shape. Speech Bubble Icon A icon displaying a speech bubble WhatsApp An icon of the WhatsApp logo. Information An icon of an information logo. Plus A mathematical 'plus' symbol. Duration An icon indicating Time. Success Tick An icon of a green tick. Success Tick Timeout An icon of a greyed out success tick. Loading Spinner An icon of a loading spinner. Facebook Messenger An icon of the facebook messenger app logo. Facebook An icon of a facebook f logo. Facebook Messenger An icon of the Twitter app logo. LinkedIn An icon of the LinkedIn logo. WhatsApp Messenger An icon of the Whatsapp messenger app logo. Email An icon of an mail envelope. Copy link A decentered black square over a white square.

Fife roadworks frustration could be repeated as bridge strengthening project delayed

The first phase of works led to long tailbacks.
The first phase of works led to long tailbacks.

A major bridge strengthening project that caused long tailbacks on one of Fife’s busiest roads has been delayed indefinitely after costs soared.

Significant repairs to the A91 New Bridge at Guardbridge, have had to be split into two phases after Fife Council exceeded its budget halfway through the works, which were much more complex than anticipated.

It means motorists travelling to and from St Andrews could face further frustration in the future when the second phase, involving the installation of a £1 million system to protect the steel, eventually begins.

Tailbacks during the first phase.

Officers said completing the project in one block was unaffordable but the work already done will protect the structure for the next 10 to 15 years, despite the amount of traffic travelling on it.

However, the risk of weakening due to corrosion remains and regular inspections will be carried out.

Work on the bridge over the Eden Estuary began in June last year and was due to be completed in April but contractors discovered it was in much poorer condition than anticipated.

The complexity of the work, along with delays due to lockdown and social distancing requirements, meant the first phase was not finished until August at a cost of £1.74m – more than the budget set aside for the entire project.

The A91 is the busiest road in north east Fife and the second busiest in the entire region and councillors have expressed concern over further traffic disruption during the second phase and the bridge’s condition in the meantime.

St Andrews Liberal Democrat Jane Ann Liston said: “I hope it’s not going to be too far down the line before the second part and completion of the work.

“That’s the busiest road in north east Fife because it takes all the cars in and out of St Andrews.

“If there is any disruption to traffic flow there it has a knock-on effect.”

SNP councillor Ann Verner described the situation as unfortunate.

“The roadworks were dreadful,” she said.

Senior roads manager Derek Crowe said the second phase would not happen within the next five years.

“We have a limited budget and have to manage the programme to fit in with the available resources.

“The A91 became unaffordable to do it in one go and we’re unable to commit in the next five years but it will follow on.

“The risk of weakening due to corrosion remains and the cathodic protection system is still required in the longer term.”

Huge queues and St Andrews to Dundee bus cancellations as Guardbridge roadworks endure